		Task # | 
		Description | 
		Results | 
		Est. duration | 
		Team members | 
	
		| 1 | 
		General project management |   | 
		1.5 hours |   | 
	
		| 1-1 | Review 
		project plan | - 
		Review minutes from kick-off meeting- Project plan is updated based on outcome of kick-off meeting
 | 1 hour | SAP 
		Business One project manager, client project manager | 
	
		| 1-2 | 
		Schedule business requirements gathering workshops | - 
		Business requirements gathering workshops are scheduled | 0.5 
		hours | SAP 
		Business One project manager, client project manager | 
	
		| 2 | 
		Business requirements gathering |   | 
		19 hours |   | 
	
		| 2-1 | 
		Conduct business requirements gathering workshops | - 
		Business needs defined in detail in the areas of: * sales,
 * purchasing,
 * inventory management,
 * production and MRP,
 * financials and accounting,
 * service management
 * banking
 * reporting
 * Business Partner and Item Master Data
 * chart-of-accounts
 - 
		Requirements defined for:* authorizations and data ownership
 * data migration
 * interfaces and integration points
 * system performance
 | 15 
		hours(5 workshops at 3 hours each)
 | SAP 
		Business One consultant, client functional leads, client IT 
		administrator | 
	
		| 2-2 | Create 
		Business Blueprint | - 
		All relevant data (requirements, solutions, limitations, and gaps) are 
		documented in Business Blueprint document | 4 hours | SAP 
		Business One consultant | 
	
		| 3 | 
		Review blueprint  |   | 5 
		hours |   | 
	
		| 3-1 | 
		Review and discuss Business Blueprint | - 
		Feasibility of business and technical requirements is determined- Limitations and gaps are established and solutions are agreed upon
 | 4 hours | SAP 
		Business One consultants, SAP Business One project manager, client 
		project manager | 
	
		| 3-2 | Review 
		project plan | - 
		Project plan is up-to-date based on Business Blueprint review | 1 hour | SAP 
		Business One project manager, client project manager | 
	
		| 4 | 
		Review Project Phase | 
		- Obtain signed project phase sign-off | 1 
		hour | 
		SAP Business One project manager, client project 
		manager, SAP Business One consultants |